Your vendor needs 10 days, Odoo promises 4

On a sales line, Odoo 19 and 20 copy the customer lead time of the product, and nothing else. For make-to-order products, the vendor lead time, the days to purchase and the manufacturing lead time are ignored by the promised date. MTO Realistic Lead Time makes the line lead time cover the whole supply chain. Free, for Odoo 19 and 20, Community and Enterprise.

  • Free
  • Odoo 19 · 20
  • Community & Enterprise
  • Odoo.sh

A promised date that ignores replenishment

With a 4-day customer lead time, a 10-day vendor lead time and 2 days to purchase, Odoo promises delivery in 4 days.

A lead time copied, not computed

For a product on Replenish on Order with Buy or Manufacture, the line keeps the customer lead time of the product, whatever chain it triggers.

A request for quotation already late

At confirmation, Odoo counts the vendor lead time back from the promised date: the request for quotation is born with an order deadline 6 days in the past.

The customer finds out too late

Nothing warns the salesperson on the quotation: the gap shows up when the goods do not arrive on the promised date.

What MTO Realistic Lead Time does

A line lead time that covers the supply chain, and a warning when the promised date is too close.

The minimum of the chain

For every line that will trigger a purchase or a manufacturing order: rule delays, vendor lead time, days to purchase, manufacturing lead time, days to prepare the MO, component picking, multi-step delivery, plus the company security lead time.

Odoo’s own calculation

Rules are found the way the procurement will find them (route of the line, warehouse, delivery steps), and the delays come from the standard planning used by replenishment.

The longest of the two

The line lead time becomes the longest of the product customer lead time and that minimum: 12 days in the example, and the request for quotation is no longer late.

A warning, not a block

A commitment date or a lead time typed too short shows a warning on the quotation, product by product: “the supply chain needs 12 days, the delivery date leaves 5”. The salesperson can still promise less, knowingly.

An optional column

The Supply Lead Time column shows the minimum on every line; products delivered from stock show 0 and keep the standard behaviour.

One calculation per product

The chain is walked once per product, not per line: a 30-line quotation costs the same queries as a one-line quotation.

Odoo quotation with the Supply Lead Time column: 12 days for the made-to-order desk, 0 for the chair delivered from stock
The line lead time covers the chain: 12 days instead of 4.
Odoo quotation with the warning: the supply chain needs 12 days, the delivery date leaves 5
A promised date too close: the quotation says so, product by product.
Standard Odoo request for quotation whose order deadline is already in the past
Without the module: the request for quotation is born with a deadline in the past.

Nothing to configure

  1. Sell a made-to-order product

    Add the product to a quotation as usual: the line lead time becomes the longest of the product customer lead time and the minimum of its supply chain.

  2. Confirm

    The expected date of the order is now reachable: the order deadline of the request for quotation is today or later.

  3. Promise too short? You are warned

    If the delivery date of the quotation, or a lead time typed by hand, is shorter than the chain, a warning lists each product concerned, with the days needed and the days left.

Frequently asked questions

Lines whose chain of rules ends on Buy or Manufacture (make to order, dropshipping). Sales from stock are unchanged.
The first one on the product form, as in the lead times of Odoo replenishment rules. Without a vendor or a bill of materials, no order is created and the line keeps the product lead time.
It is counted as an order: a cautious estimate, even if the stock could serve the order.
When the product, route or warehouse of the line changes, like the standard lead time. Changing a vendor lead time later does not rewrite existing quotations; the next ones use it.
Odoo 19 and 20, Community and Enterprise: the module only depends on sale_stock; purchase, manufacturing and dropshipping lead times are used when those apps are installed. It works on Odoo.sh and on your own server, not on Odoo Online.
Like any module. Nothing is stored besides the lead time of the lines, which stays as computed.